Beneficiation & Pellet plant at Honduras:
Our Challenges
– The major challenge was fluctuating characteristics of different minerology of Iron ore coming from mine.
– Key challenge was limited budget for capital expenditures.
– Limited land availability
– End user of having different process route.
– Stringent environment norms is one of the key challanges
Our Solutions
– Stage wise testing of raw material with different agencies done, as per test reports process flow developed.
– To minimise capital expenditure sourcing of equipment and structures done from India under make in India initiatives.
– Proper utilization of land done while preparing plant layouts.
– Special Pellet coating system designed, so that pellets can be used through Midrex and HYL route.
– Indigenous developed desulphurisation system using wet flue gas scrubbing process.